GTRI Project Update: Upcoming Roadworks and Construction Schedule for Edward Street
The Ministry of Planning, Agriculture, Housing, Infrastructure, Transport & Development (PAHITD) announces the upcoming construction activities for the George Town Revitalisation Initiative (GTRI). The next phase of roadwork and paving will focus on Edward Street, with works scheduled over the upcoming weekend. This stage is crucial for improving infrastructure and enhancing the overall safety and accessibility of the area.
The schedule is as follows:
• October 12, 2024: Island Paving will conduct road paving activities on sections of Edward Street. To minimize traffic disruptions, paving will occur during the night hours. We advise motorists and residents to be aware of potential road closures or restrictions during this time.
• October 13, 2024: The National Roads Authority (NRA) will restripe Edward Street and install new signage. These activities will commence in the morning and continue until completed. These upgrades are part of ongoing efforts to enhance traffic flow and pedestrian safety in the area.
• October 13, 2024: Robson Construction will move into the work zones 2b-3 and 2b-4. This includes the installation of Heras fencing, cones, and other necessary safety measures to secure the work areas.
• October 14, 2024: Robson Construction will begin significant works in the designated 2b-3 and 2b-4 zones. The Ministry will continue to update the public as the project progresses and appreciates the community’s patience and cooperation during this period of transformation.
Residents and businesses along Edward Street are encouraged to plan accordingly as these scheduled activities may cause minor disruptions. For any questions or concerns regarding the upcoming works, please contact the George Town Project Manager, Mr. Colin Lumsden, Direct: 345-244-2475 or Email: colin.lumsden@gov.ky
The George Town Revitalisation Initiative is part of the Cayman Islands Government’s broader strategy to improve infrastructure, promote economic growth, and enhance the quality of life for all residents and visitors. We thank the public for their continued support as we work towards a better future for George Town.
For more information about the George Town Revitalization Initiative and its ongoing projects, please visit www.georgetownrevitalisation.com .
06 Apr, 2020
13 Apr, 2020
12 Apr, 2020
Comments (0)
We appreciate your feedback. You can comment here with your pseudonym or real name. You can leave a comment with or without entering an email address. All comments will be reviewed before they are published.